How do I mark a task as highlighted or critical?

D

Dina

I realize I cannot change the font for the text in the Calendar view so now I
thought I woud attack the problem by marking the tasks as
marked/highlighted/critical/noncritical, but can't find how to do that either.
 
D

DavidC

Hi Dina,

If you select the name column and right click, there is a function 'Text
styles'. Select this and look at the drop down box 'Item to change', this
identifies a number of task types where you can set the font type, style and
colour.

Hope this helps

Regards


DavidC
 
J

Jan De Messemaeker

Hi,

Marked: insert the column "Marked" in a tk sheet view, put to "Yes"
Highlighted: for filtered tasks, with the "Highlight filter" option on
To put it on, activate Calendar view, View menu, More views, edit, you see
the checkbox
Critical: is calculated by Project depending on the relationships. Cannot be
set
Hope this helps,

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
Dina said:
I realize I cannot change the font for the text in the Calendar view so now I
thought I woud attack the problem by marking the tasks as
marked/highlighted/critical/noncritical, but can't find how to do that
either.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top