How do I reset the project start date?

J

Jean

I have a project that has been put on hold. I now need to reset the start
date in Project. When I go to Project | Project Information and reset the
Start date, the dates are not recalculated in the body of the plan. What
should I do?
 
J

JulieS

Hi Jean,

If you have constraints on tasks in the project, updating through Project
Information may not move the tasks. Show the Analysis toolbar and click on
the Adjust Dates button.

Hope this helps. Let us know how you get along.
Julie
 
J

Jan De Messemaeker

Was any of the work entered as done?
In that case you cannot automaticallly reset the start date (Project is very
willing to update your plan, but it won't change history - only kings did
that in the past) but the good news is that you can automatically reschedule
the unfinished work to after a certain date:
Tools, tracking, Update Project, it is well explained there.
HTH


Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top