G
graham
I've created a 610 line project in 2003, using manual entry, and all dates
and durations that I have entered and constrained, are correct.
Problem: This is revision (or attempt), oh, 200, of this schedule, and I
have yet to find a way for the Summary Tasks to indicate correct
dates/durations without allowing Project to 'calculate' the project. When
Project calculates what I have entered all my tasks go to 'h***'. Is there a
way to block Project from trying to 'correct' over allocations, etc...
Hope to achieve: I would prefer keeping the schedule as manual entry and
have it roll up accurate durations in summaries, as I have not found a fool
proof way to show accurate results using any of Projects' automated features.
Background: I have purchased, digested and applied Wileys's Project 2003
Bible, and 'for Dummies'. Hundreds of hours in, and no solution, other than
a conclusion that Project is 50% entry and 50% fight with software for
correct results.
Help!!!
and durations that I have entered and constrained, are correct.
Problem: This is revision (or attempt), oh, 200, of this schedule, and I
have yet to find a way for the Summary Tasks to indicate correct
dates/durations without allowing Project to 'calculate' the project. When
Project calculates what I have entered all my tasks go to 'h***'. Is there a
way to block Project from trying to 'correct' over allocations, etc...
Hope to achieve: I would prefer keeping the schedule as manual entry and
have it roll up accurate durations in summaries, as I have not found a fool
proof way to show accurate results using any of Projects' automated features.
Background: I have purchased, digested and applied Wileys's Project 2003
Bible, and 'for Dummies'. Hundreds of hours in, and no solution, other than
a conclusion that Project is 50% entry and 50% fight with software for
correct results.
Help!!!