In order to see if tasks are slipping you need to make sure you update
your project and then move any incomplete work forward in time. Add
progress details (Actual Start, Actual Finish, Actual Work, Remaining
Work etc) and then use the Update Project command in Tools > Tracking
Update Project, with the option "Reschedule uncompleted tasks to start
after".
That will move the remaining work and duration forward to the date you
specify and the slipping task report should now make much more sense.