How do I save the resource schedule as a baseline in MS Project?

T

tornadosgrl81

I am having a little difficutly with my MS Project work. I am not very
familar with this program and have just started learning. I need to know how
I can save a base line in my resource schedule?
 
J

JulieS

Hi Tornadosgrl81,

You may save a baseline for your project with Tools>Tracking> Save Baseline.
You may view baseline data for your project by applying the Baseline Table
to the Gantt chart (View>Table>More Tables...Baseline) or you may view
baseline resource information in the Work or Cost table applied to the
resource sheet.

Mike Glen (Project MVP) has written a good series of articles that may help
you learn more about Project. You may view the articles at:

http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23

I hope this helps. Let us know how you get along.

Julie
 