L
Lori O
I read a message thread for this very problem. Basically I want an 8hr task
to to have a duration of 5 days. (Why, because resource is only given a small
window of time each day to work on the task.) The answer given was to change
the task type to fixed duration. When I go into the task and set it up for
8hr with the start and end dates over 5 days and change the task type to
fixed and click ok, the start date still changes to the same day as the end
date. In other words it is making my duration only one day. HOW do I make
the start and finish days "stick"?
to to have a duration of 5 days. (Why, because resource is only given a small
window of time each day to work on the task.) The answer given was to change
the task type to fixed duration. When I go into the task and set it up for
8hr with the start and end dates over 5 days and change the task type to
fixed and click ok, the start date still changes to the same day as the end
date. In other words it is making my duration only one day. HOW do I make
the start and finish days "stick"?