Rebecca Wenberg
I am required to keep O&M project plans. They start 10-1-04 and end 9-30-05.
Therefore, regardless of the amount of work done or remaining, after 6
months, the project is 50% complete.
How can I show the actual amount of hours worked, without Project
automatically updating the Percent Complete column. It is entirely possible
that some O&M projects will have 95% of the hours completed for the year
before the 6 months is up, but the project is still only 50%.
I've seen that you can Click Tools | Options and go to the Calculation tab
to clear the 'Updating task status updates resource status' check box. But
even after clearing this box, the percentage complete and Actual Hours are
still connected and updating each other.
Thanks for any help you can give me on this.
Therefore, regardless of the amount of work done or remaining, after 6
months, the project is 50% complete.
How can I show the actual amount of hours worked, without Project
automatically updating the Percent Complete column. It is entirely possible
that some O&M projects will have 95% of the hours completed for the year
before the 6 months is up, but the project is still only 50%.
I've seen that you can Click Tools | Options and go to the Calculation tab
to clear the 'Updating task status updates resource status' check box. But
even after clearing this box, the percentage complete and Actual Hours are
still connected and updating each other.
Thanks for any help you can give me on this.