How do I set previous order dates for tasks%3f

D

dvlesus

I'm new to this software and I am wondering if I can set up a previous
reminder to a task that will show up on the calendar and graph? ie. Need to
oder product 3 weeks before beginning a task.
 
J

JulieD

Hi

i would put
"Order Product"
in as a separate task and link it to the task that utilises the product - if
you want the timing of the task utilising the product to drive the timing of
ordering of the product you can use a SF constraint with the utilise product
task as the predecessor.

Cheers
JulieD
 