How do I set up a planning on hour-base? Eg task 09:00-12:00.

M

Melvin

I want to be able to enter any hour-based time as start of a task. Thus eg.
09:00 starttime and 12:00 endtime.
What I've discovered till now is that the starttime only can be planned from
a daily base.

BR and thanks!

Melvin
 
R

Rod Gill

HI,

Simply add a time to the end of the date, EG 9/9/2008 09:00
Under Tools, Options and the View tab, select a date format that shows time
as well.

Note that the more dates and times you enter, the less useful your schedule
becomes and the more manual edits you will need to make. It's much better to
have one start date then link all tasks together so that start and finish
dates and times are calculated for you.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 