I want to setup a meeting that occur every week. These meeting should be
visible at the gannt chart. Can you help me.
 
G

Gérard Ducouret

Hello Søren
Try the following :
Insert / Recurring task / Recurrence pattern : Weekly...

Gérard Ducouret
 
K

Kelly

Once I create a recurring task, like a weekly status meeting, it shows them
all together on the timeline; how to I sort them by start date, so the weekly
tasks are incorporated into the timeline?
 
G

Gérard Ducouret

Hello Kelly,
I'm not sure of what you want, but...
Click the "+" sign on the left of your recurring task name
Hope this helps,

Gérard Ducouret
 
J

JulieS

Hi Kelly,

If I understand your question correctly, I think there may be a
workaround that you can use to accomplish what you want. When you
create recurring tasks they are grouped together under the summary
recurring task and won't sort correctly as it will sort by the start
date of the summary task.

Select all of the subtasks under the summary recurring task and outdent
them to make them no longer subtasks of the summary recurring task.
Then you can sort the project by start date to distribute the status
meeting tasks among the rest of the tasks in the project. (You will
most likely want to delete the task which used to be the summary
recurring task.)

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top