how do I set up a t-minus schedule in Project?

C

CraigF

I have a 21 day notice to complete a project with many main and sub-tasks.
How do I set it up such theat the dates are not hard but rather based on the
notice period?
 
J

Jan De Messemaeker

Hi,

What makes you think dates would be hard?
You have to tellk project explicitly when you want a date to be hard.
Enter your tasks, link them as the relationships dictate.
Set a deadline on the last task (Task Information, Adva,nced tab)
Now insert the columns "Late Start" and "Late Finish"

HTH
 