M
mocharaspberrygrande
My sub task are showing 100% complete but the major phases, which should
automatically show a corresponding % complete above zero, continue to show 0%
complete. Project will not let me manually change the major phase %
complete.
automatically show a corresponding % complete above zero, continue to show 0%
complete. Project will not let me manually change the major phase %
complete.