How do I show specific times of day within the duration field?

S

suttercv

Need to show 8:00PM - 11:00 PM within the duration field of MS Project, for
instance.
 
R

Rod Gill

Project doesn't support that, especially as duration is in weeks, days,
hours or minutes and never time. Start and Finish dates have date and time.
If those two together aren't enough, create a formula in a Text field to
concatenate the two dates or times.
 
M

Mike Glen

Hi suttercv ,

Welcome to this Microsoft Project newsgroup :)

You can't. However, Tools/Options.../View tab allows you to selet the Date
format to show the times of day, if that's of any use to you.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top