How do I show the date a task's baseline was set in Project?

J

John Doe

I need to individually baseline tasks rather than all the project at once and
later need to show when I baselined a particular task. I would like a column
that shows the date a task was last baselined and if a task has not been
baselined, it should just be blank.
 
P

Project Slave

You can baseline individual tasks by going to tools>tracking> sava baseline >
selected tasks.

Insert a custom data column (insert>column>select one of Date 1 to 10),
rename it appropriately and enter baselined date manually.
 
J

John Doe

Thanks,

Unfortunately, as dates slip, WHEN a task was baselined can be controversial
in my organization so manually inputting a date takes away from the integrity
of the plan + NOW it would be nice to know when all those other tasks were
baselined. I will use your solution for future baselines unless I get a
better idea.

Take care-----------john
 