How do I span a 50 hrs task throughout the 3 months of my project.

D

Deepak Kumar

How do I span a 50 hours task throught out the 3 months of my project?
Because, if I enter the duration (hrs) and then the start date, MS Project
calculates the finish date automatically...which i don't want. I want to add
my finish date, which it doesn't allow. Why is this? or am I doing something
worng or is there any solution for this requirment? This task will run as a
parallel task through out the project.
 