F
Franknhs
I have a training task that produces resources (trainers) for use on later
tasks. If the training task is delayed then later tasks, which require
trained resources, either cannot take place or will take place more slowly
because fewer resources will be available. At the moment I have to change
the number of resources available for later tasks manually, can this
relationship be automated? I use MS Project 2002.
tasks. If the training task is delayed then later tasks, which require
trained resources, either cannot take place or will take place more slowly
because fewer resources will be available. At the moment I have to change
the number of resources available for later tasks manually, can this
relationship be automated? I use MS Project 2002.