How do I view my successor tasks who's predecessor was completed?

S

StumpinSeattle

I would like to know how I can have Project show me all my next sucessor's
task who's predecessor was completed? I am not as scheduled driven as "next
task to completed" driven.

AZ
 
J

Jan De Messemaeker

Hi,

Wel, so am I, I can tell you how I handle this.
Of course, when I track the finished tasks, if necessary I also change the
finish date.

Then through Tools, Tracking, update Project, Reschedule uncompleted work...
I shift all these "sucessors with finished predecessors" to start after the
date I have selected

Then with Auto Filter I can filter on that start date.
HTH
 
S

StumpinSeattle

Thank you Jan. My real stump is how do I customize a field to tell me the
all dependent "successors" task of a completed "Predecessor" are "ready" and
the rest of the the rest of the " successors' " successors are "Pending". I
would assume that it is an IIF statement?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top