K
Kevin
I've been playing around with my project file, and I
realized now why my critical path does not show the way I
would expect. All of my tasks are setup as fixed work
tasks. I then assigned a single resource to each of them
at 60% time (this is basically how our projects work).
After making these resource assignments, most of the tasks
I would expect to show in the critical path are no longer
there. Can someone please explain how the critical path
is calculated when it comes to resources and fixed-work
tasks?
Thanks for any help- I'm not finding much rhyme or reason
to this.
realized now why my critical path does not show the way I
would expect. All of my tasks are setup as fixed work
tasks. I then assigned a single resource to each of them
at 60% time (this is basically how our projects work).
After making these resource assignments, most of the tasks
I would expect to show in the critical path are no longer
there. Can someone please explain how the critical path
is calculated when it comes to resources and fixed-work
tasks?
Thanks for any help- I'm not finding much rhyme or reason
to this.