I have been just getting started using MS Project 2003 and for the love of me
can't find how to establish a projects deadline>>>>....Can anyone help with
this?

Thanks
 
J

JulieS

Hello,

You can place a deadline on the final milestone in the project. To
place a deadline double click on the task to show the task information
dialog box. Click the Advanced tab and enter or select a date in the
Deadline area. Click OK to close the dialog box. The deadline
indicator (green outlined arrow) will appear in the Gantt chart. If the
task slips past the deadline, an indicator will appear in the indicator
column.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top