D
Dave H
I'm having trouble with resource allocation. It seems to go off in the weeds
when entering resource information.
I have this information upon which to build a project: man-hours of work,
resource names, and resource calendars (5 resources, 3 different resource
calendars)
After building the task using the man-hours of work with a Fixed Unit task
type, I come back to add resources. Everything works fine the first time I
put in the resources. But the resource allocation seems to go off in the
weeds if I come back and make changes to resources with a resource using a
different calendar than the base calendar. It doesn't seem to distribute
the work among the resources correctly to get the task done in the least
duration.
Any ideas?
Dave H
when entering resource information.
I have this information upon which to build a project: man-hours of work,
resource names, and resource calendars (5 resources, 3 different resource
calendars)
After building the task using the man-hours of work with a Fixed Unit task
type, I come back to add resources. Everything works fine the first time I
put in the resources. But the resource allocation seems to go off in the
weeds if I come back and make changes to resources with a resource using a
different calendar than the base calendar. It doesn't seem to distribute
the work among the resources correctly to get the task done in the least
duration.
Any ideas?
Dave H