Hi Simon,
In addition to Dave's suggestion, if you level from a resource view
(such as Resource Usage) you can select the specific resource and when
prompted by the Resource Leveling command, choose "Selected Resource"
instead of "Entire Pool".
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project