How to change all dates of a project plan

I

Inge

Hi,

I have composed a project plan with tasks/dependencies about 6 months ago
and now, we have the final GO of the project.

How can by changing just the start date for this project, let all the other
dates adjust themselves automatically, repecting the tasks' dependencies?
 
J

JulieS

Hi Inge,

Assuming your tasks are linked without any constraints:
Go to Project > Project Information and then set the new start date of
the project.

If you have constraints (Start no Earlier than, Start no later than,
etc.):
Display the Analysis toolbar and click the Adjust Dates button.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 
I

Inge

Hi Julie,

thank you so much for your quick help: I had tried project, project
information already, no luck (because of the constraints), but now tried your
option with the analysis toolbar and it is perfect now.

Thanks again
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top