H
Hugues Perron
Hi, I need to create a sub-project from a master project based on some
criteria (I won't use the filters on Project beacause I really need two
project files).
So I'm writing a program that creates a new project and copy the selected
tasks in it. The problem is I need to copy all the information (including
the actuals, the predecessors, etc...). Is there a way to copy all the
information of a task (like a Copy & paste) or do I have to copy each field
(which is a complex and long task) of the task.
I use VB, not VBA, the program must be stand alone.
Help will be very appreciated.
Thanks
Hugues
criteria (I won't use the filters on Project beacause I really need two
project files).
So I'm writing a program that creates a new project and copy the selected
tasks in it. The problem is I need to copy all the information (including
the actuals, the predecessors, etc...). Is there a way to copy all the
information of a task (like a Copy & paste) or do I have to copy each field
(which is a complex and long task) of the task.
I use VB, not VBA, the program must be stand alone.
Help will be very appreciated.
Thanks
Hugues