Suppose some activities only start on 'odd' days, and some on 'even'
days, is there a way to impose such constraints in MS Project?
I am trying to use it to schedule college courses that require pre-
requisites. I use days to represent semesters, and there are courses
that are offered only in the 'odd' or 'even' semesters.
Thanks!