How to keep PWA timescale/duration (week) same PP

T

TuDao-21Aug

Hi
I have made project with Timescale by week in Project Professional 2003 but
when I published it & viewed by Project Center or PWA, timescale is back to
date ! Same for Duration.

May someone help

Thanks
 
D

Dale Howard [MVP]

TuDao --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the Microsoft Project desktop application only. To answer your question,
how you set the level of zoom for the Timescale bar in Project Professional
2003 has NOTHING to do with the level of zoom for the project when viewing
it in the Project Center page in PWA. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top