Microsoft's Team Foundation Server only synchronizes with Microsoft Project
tasks if there are not more than one resource tied to a task -- so the
workaround until version 2 is to create 2 tasks with the same name and
duration and assign each to a different resource. The problem with this is
that when I level the plan it does not necessarily hold these two tasks
together. I tried setting a start to start dependency between the 2 tasks,
but you know that just means task A can't start until B does -- not ensuring
that they start and finish together of course. Any ideas?
tasks if there are not more than one resource tied to a task -- so the
workaround until version 2 is to create 2 tasks with the same name and
duration and assign each to a different resource. The problem with this is
that when I level the plan it does not necessarily hold these two tasks
together. I tried setting a start to start dependency between the 2 tasks,
but you know that just means task A can't start until B does -- not ensuring
that they start and finish together of course. Any ideas?