how to make a task 'stretch' to fill the time availavble?

D

Doug

Good morning,

I am trying to do something with this 'wonderful' tool,
and need some help. I will describe the problem in 2
ways, let me know if you have any insights, or if there is
anyone else to ask.

thanks
Doug


Sciforma PS8 code language:
Does MS-Project do what ps8 called hammock tasks?


Longer description:
I want to build a schedule where there are certain tasks
which have a fixed start, their end date is FF linked to a
milestone, and the tool calculates the duration and fills
it in. All of the incantations I have tried with Project
will not 'stretch' the task out to fill the time available
to it. The duration is always fixed and I am just moving
the task around.
 
M

Mike Glen

Hi Doug,

Welcome to this Microsoft Project newsgroup :)

A hammock might meet your needs - please see FAQ Item: 19. Hammock Tasks.
FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
S

Steve House

Are you choosing "paste link" with a data type of "text data" when you try
to insert the date into the stsart date column? And are you pasting into
the start date in the Gantt chart entry table or into some other date field?
 
B

Bryan A

I double checked and Yes to all.


Steve House said:
Are you choosing "paste link" with a data type of "text data" when you try
to insert the date into the stsart date column? And are you pasting into
the start date in the Gantt chart entry table or into some other date field?
 
T

travis meyer

You may want to try splitting the task.....email me with
PROJECT in the subject if this does not work....
travis
 
S

Steve House

Is there a dependency link going into or coming out of the task you're
trying to paste into?
 
J

Jan De Messemaeker

Doug,

You cannot "HAMMOCK" a summary task
That gives the error message you describe
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
J

Juergen Stock

Doug,

it's true, you cannot hammock a task BUT you can emulate
one.
Link a milestone Start-to-start to the task you want to
adjust to and link another milestone Finish-to-finish to
the same task. Then move these two milestones under a new
summary (which sould contain only these two milestones)
and this summary will then stretch (or shrink).

As you can assign a resource to a summary your emulated
hammock would contribute to the overall work and cost.

Regards,

Juergen
 