Good morning,
I am trying to do something with this 'wonderful' tool,
and need some help. I will describe the problem in 2
ways, let me know if you have any insights, or if there is
anyone else to ask.
thanks
Doug
Sciforma PS8 code language:
Does MS-Project do what ps8 called hammock tasks?
Longer description:
I want to build a schedule where there are certain tasks
which have a fixed start, their end date is FF linked to a
milestone, and the tool calculates the duration and fills
it in. All of the incantations I have tried with Project
will not 'stretch' the task out to fill the time available
to it. The duration is always fixed and I am just moving
the task around.
I am trying to do something with this 'wonderful' tool,
and need some help. I will describe the problem in 2
ways, let me know if you have any insights, or if there is
anyone else to ask.
thanks
Doug
Sciforma PS8 code language:
Does MS-Project do what ps8 called hammock tasks?
Longer description:
I want to build a schedule where there are certain tasks
which have a fixed start, their end date is FF linked to a
milestone, and the tool calculates the duration and fills
it in. All of the incantations I have tried with Project
will not 'stretch' the task out to fill the time available
to it. The duration is always fixed and I am just moving
the task around.