How to mark all sundays at 200/hr ?

M

Milind

Hello
My resource works only on Sundays. In Resource Information, A (default tab),
how do I mark all sundays at 200/hr? If my project lasts 9 months, do I have
to physically mark all of them? Or is there any other way out?
Milind
 
G

Gérard Ducouret

Hello,

Create a new calendar :
Tools / Change working time / New... give a name to your new calendar...
Select the Sunday column and click Nondefault working time
Select all the other columns and click Nonworking time
OK

In the Resource Sheet view, apply this calendar to all the appropriate
resource.

Assign the resource on tasks with Unit = 25 (if 8h/day)