I need to merge two tasks into a single one but do not want to loose any
information in the process. E.g. the actual work is currently maintained
separately in the two tasks. How do I merge them without loosing the actual
work values?
 
M

Mike Glen

Hi Zappy,

Welcome to this Microsoft Project newsgroup :)

I don't think this is possible, though a vba program might be offer a
solution. I would enter the actual data give both tasks zero remaining
work. Then create a new task to finish the work.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top