You can always open up an old plan and then use "save as" and give it a new
name. Then use Project/project Information/Start date and change this to the
new start date. There may be some additional work such as zeroing out actual
work, and removing resources
Thanks for replies . Actual work has been brought back to zero and
Project/project Information/Start date have been changed . Still dates
activities dates remain unchanged !
As soon as actual work has been put to zero, constraints take over!
Either select all tasks, click the task information icon, advanced, set teh
constraint to as soon as possible or
Show the analysis toolbar, run adjust dates
OR in earlier versions (<2002) tools, macro, macros, adjust_dates, run.
HTH
In Project 2003 File menu select New. ON the New File task pane, select
"From Existing Project" and select the one you wish to copy. A new file
will be created based on the content of the old one. Remove actuals and
change start date
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.