I've saved a baseline for my project. I now need to change duration for
some tasks and I've inserted a new column Finish 1. However, when I change
the duration, the Finish column changes while Finish 1 still displays NA.
What am I doing wrong?
Thank you.
 
D

Dale Howard [MVP]

Melissa -

You can find your original finish date for the task in the Baseline Finish
field. Hope this helps.
 
M

Melissa

Thanks for the speedy response! I've actually used Baseline before but
forgot all about it! :p
 