I accidently added a constraint is there any way to remove it?

R

Richard

I set a start date for a task in project. Now I have decided it would be
better to have the task start when a predecessor is complete. Is there
anyway to remove the constraint?
 
J

John

Richard said:
I set a start date for a task in project. Now I have decided it would be
better to have the task start when a predecessor is complete. Is there
anyway to remove the constraint?

Richard,
Sure, select the task and go to Project/Task Information/Advanced tab.
Change the Constraint type to be "As soon as possible". Or you could
display the Constraint Type field in the view and change it there from
the drop down list.

Hope this helps.
John
Project MVP
 
D

Dale Howard [MVP]

Richard --

Double click the task in question and then select the Advanced tab in the
Task Information dialog. Set the Constraint Type field to As Soon As
Possible and then click the OK button. This will resolve your problem.
Hope this helps.
 