Sannas

Is there a way to identify split tasks in the schedule EXCEPT for the split
task indicator on the Gantt chart view? I would hope there would be a column
or underlying switch somewhere that identifies the task as split?

Thanks for your help!
 
G

Gérard Ducouret

Sannas,

You could create this indicator in a custom field with a formula like this
one :
IIf(ProjDateDiff([Start];[Finish])<>[Duration];"Split";"")

Hope this helps,

Gérard Ducouret
 
S

Sannas

Wow! I never would have approached it like this! It's amazing and thanks
for the input!

Sannas

Gérard Ducouret said:
Sannas,

You could create this indicator in a custom field with a formula like this
one :
IIf(ProjDateDiff([Start];[Finish])<>[Duration];"Split";"")

Hope this helps,

Gérard Ducouret

Sannas said:
Is there a way to identify split tasks in the schedule EXCEPT for the split
task indicator on the Gantt chart view? I would hope there would be a column
or underlying switch somewhere that identifies the task as split?

Thanks for your help!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top