Import wizard problem

V

Vit

Hi All,

I'm trying to import data frm excel using the "import wizard" option,
to map the MS Project Field with the MS Excel Column...

I don't know why, but there is a problem...

I'd like to import:

- Task Name
- Duration
- Work
- Task QTY (enterprise custom field)
- Units (enterprise custom field)\

I can easy import Task Name, Duration and Work, but I'm not able to
import Task QTY and units...

when I use the wizard, it seems to be everything OK... no error
messages...

but the fields are empty...

why???

for example, Task QTY is a number (in the project side) and the column
in excel is a number too...

units is a look un table in MS Project, and in Excel there are the
same value...

the Fields should be visible in the gantt view???

what can be the problem???

thank you so much...

Cheers

Vit
 
M

Manmeet Chaudhari

Hi Vit

When you are importing data from MS Project to Excel it is advisable to
create a new Map in the wizard.

In the new map you can enlist all required columns including the custom
columns Task Qty and Units

This will ensure that the custom columns also appear in Excel

Hope this helps.

Thanks,
 
V

Vit

hi Manmeet Chaudhari,

I'm trying to do the opposit... from excel to project...

I have alteady map the field and the column, but the data isnot
imported... why???

thanks

Cheers

Vit
 
M

Manmeet Chaudhari

Hi
When mapping the fields are you choosing the correct data type like number,
text ....
What version of MS Project are you using?

Thanks
Manmeet
 
V

Vit

Hi,

MS Project Pro 2007 and MS Excel 2003

number to number and text to text....

thanks

Vit
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top