J
Jimbo
I have a data export for work from SAP into Excel. I have my project set up like I want it to be. The only defaults for new task added are 'from project start' and 'from todays date'.
When I paste my data into the project the system does just what is says it will do and schedule my dates from the project start.
I then have to copy the dates/times from the excel data sheet and paste them into the start date field. This works but takes more time.
Does anyone know a better way to put previously scheduled dates into project without the recopy and paste requirement.
I'm Using MS Project Pro 2003.
Thanks
When I paste my data into the project the system does just what is says it will do and schedule my dates from the project start.
I then have to copy the dates/times from the excel data sheet and paste them into the start date field. This works but takes more time.
Does anyone know a better way to put previously scheduled dates into project without the recopy and paste requirement.
I'm Using MS Project Pro 2003.
Thanks