In the import option, I am trying to import tasks that I
have in an excel file. I am unable to get the correct
headings to display to "Map". Should they be named the
same as the headings in Project?
 
G

Gérard Ducouret

Hello Joe,
The headings can be different, but in the Excel file the headings must be on
the row #1
Tell us if it works !

Gérard Ducouret [Project MVP]