Hello Huggy,
Go to Tools > Change Working Time, select the Project calendar you are
using if necessary. Toward the bottom of the Change Working Time dialog
box, click the Work Weeks tab. Click the Details... button to show the
Details dialog box. Under the Select Days section, click Sunday to
select it, press and hold down the CTRL key and select Saturday. Both
Sunday and Saturday should be selected (blue). Click the option "Set
days to these specific working times" and enter the start time and end
times as you need. (For example to mimic the standard time for Monday
through Friday --
From 8:00 am To 12:00 pm
From 1:00 pm To 5:00 pm
Click OK to close the Details dialog box. Click OK to close the Change
Working Time dialog box.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project