Hi there -
I've set my calendar options to have an 8 AM - 4:30 PM day, set my hours in
a day to 7.5, and modified my standard calendar to have all weekdays be from
8-12, 1-4:30 to match the 7.5 hours in a day setting.
If I create a one day task, in the Gantt Chart view, when the timescale is
set to show days & hours, the task shows as running from 8 - 5 PM. When I
switch to hours & minutes, the task shows (correctly) as running from 8 -
4:30 PM.
I have updated my version of Project to SP2.
Any ideas what might be going on, or is this a known bug?
Thanks!
Kiron
I've set my calendar options to have an 8 AM - 4:30 PM day, set my hours in
a day to 7.5, and modified my standard calendar to have all weekdays be from
8-12, 1-4:30 to match the 7.5 hours in a day setting.
If I create a one day task, in the Gantt Chart view, when the timescale is
set to show days & hours, the task shows as running from 8 - 5 PM. When I
switch to hours & minutes, the task shows (correctly) as running from 8 -
4:30 PM.
I have updated my version of Project to SP2.
Any ideas what might be going on, or is this a known bug?
Thanks!
Kiron