P
Peters
Hello,
When leveling resources in MS Project 2007 I get completely off the chart
finish dates on some tasks. The finish date typically could be about 30 years
from now, but duration for the particular task is still 1 day. This happens
on some tasks and I have tried to figure our what the common denominator is
for these tasks, but don't get it. Can anyone tell me what the problem is and
how I solve it?
Thanks,
Peter
When leveling resources in MS Project 2007 I get completely off the chart
finish dates on some tasks. The finish date typically could be about 30 years
from now, but duration for the particular task is still 1 day. This happens
on some tasks and I have tried to figure our what the common denominator is
for these tasks, but don't get it. Can anyone tell me what the problem is and
how I solve it?
Thanks,
Peter