N
Nikou
Hi,
In the project schedule, I have mostly 2 or 3 resources assigned to each
task.I increased the percentage unit of a resource to 60% instead of 50%.
But, the Project doesn’t recalculate task durations or Project duration. Do
you know what could be the problem?
Thanks for your help,
Nikou
In the project schedule, I have mostly 2 or 3 resources assigned to each
task.I increased the percentage unit of a resource to 60% instead of 50%.
But, the Project doesn’t recalculate task durations or Project duration. Do
you know what could be the problem?
Thanks for your help,
Nikou