When I indent several items for a heading I might have
twenty days over the several items but the duration days
on the heading does not jive with the total amount of
days. This happens wether I use work days or elapsed
days. Can anyone give me an understanding of this issue?

Thanks

Mike Mc
 
J

John

Mike,
It doesn't matter how many levels of indention are present. The Duration
of a Summary line is always the difference in Project calendar days
(working days) between the Start date of the first subtask and the
Finish date of the last subtask.

Hope this helps.
John
 