I have a project file which is a combination of ten other Projects
which have been inserted.
When I open this consolidated view, then all these sub projects appear
on the gantt cart to have started on 2003-01-01, even though the Start
Date say 2006-01-01.
The minute I show all levels, then it corrects itself to show
2006-01-01 in the Gantt chart.
Can I not make this permanent? I want to open the master file and see
everything as it is now.