D
DJ Huff
Using MSP 2007 Pro but saving in 2003 std...I need to manage multiple plans
that I am inserting into a Master Plan. Each subplan uses the same template,
but when inserted, I cannot figure out how to see an accumulation of all
plans for a particular set of summary tasks. For example, if I have a
template plan with the following that I give to each team to fill out for
their activities (each team may not address each task).
Summary Task 1
Detailed Task A
Detailed Task B
...
Summary Task 2
Detailed Task C
Detailed Task D
Detailed Task E
...
Let's say Team A and Team B each address Summary Task 1 in their respective
subplans. I cannot get accumulated EVA metrics for Summary Task 1 for the
project, only for each individual subplan. Thus, I may get EVA metrics for
Team A Summary Task 1 and then a separate calculation for Team B. I need
both together.
that I am inserting into a Master Plan. Each subplan uses the same template,
but when inserted, I cannot figure out how to see an accumulation of all
plans for a particular set of summary tasks. For example, if I have a
template plan with the following that I give to each team to fill out for
their activities (each team may not address each task).
Summary Task 1
Detailed Task A
Detailed Task B
...
Summary Task 2
Detailed Task C
Detailed Task D
Detailed Task E
...
Let's say Team A and Team B each address Summary Task 1 in their respective
subplans. I cannot get accumulated EVA metrics for Summary Task 1 for the
project, only for each individual subplan. Thus, I may get EVA metrics for
Team A Summary Task 1 and then a separate calculation for Team B. I need
both together.