There might be some few tasks that have been scheduled manually, i.e. the
start and end dates as well as the resources have been set manually so that
there are no overallocations. For all other tasks, possible overallocations
should be resolved somehow without touching these manually scheduled tasks.
How is it possible to exclude these manually scheduled tasks from leveling?
Thank you,
Giannis
start and end dates as well as the resources have been set manually so that
there are no overallocations. For all other tasks, possible overallocations
should be resolved somehow without touching these manually scheduled tasks.
How is it possible to exclude these manually scheduled tasks from leveling?
Thank you,
Giannis