I sometimes get Tasks in a plan that seem to have uneditable properties
following leveling. For example I have a Task with:
start date of 12/01/09,
Actual Start of 12/01/09,
8 hours work,
100% work complete,
100% complete,
Fixed Work,
0 levelling delay
start ASAP,
.....but a FINISH of 9/06/09 and Preleveled Finish of 9/06/09.
Clearing Leveling does not adjust this date and I cannot edit manually.
I get this type of problem a lot with projects after applying levelling
several times and it is the cause of most leveling overallocations. Is there
a way i can resest these tasks without having to insert a new task, copy
values and delete the original each time?
Thanks for your wisdom
following leveling. For example I have a Task with:
start date of 12/01/09,
Actual Start of 12/01/09,
8 hours work,
100% work complete,
100% complete,
Fixed Work,
0 levelling delay
start ASAP,
.....but a FINISH of 9/06/09 and Preleveled Finish of 9/06/09.
Clearing Leveling does not adjust this date and I cannot edit manually.
I get this type of problem a lot with projects after applying levelling
several times and it is the cause of most leveling overallocations. Is there
a way i can resest these tasks without having to insert a new task, copy
values and delete the original each time?
Thanks for your wisdom