Hi,
In Excel there are two ways to drag down, and you do not specify which one
you want.
If you want to copy the same value down, there are two ways in Project: you
can "grab" the lower left corner and drag as in Eccel or wou can specify the
range and type Ctrl+D to copy down.
If you want to increment the predecessor ID by 1 each time, that cannot be
done by dragging in Project. However, you can select the tasks to be
sequentuiially linked and click the "Link Tasks" icon on the Standard
Toolbar to link them in sequence.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional