Is there a possibility to increment predecessors as in excell ?

L

Laurian Anania

For example to drag down the first two consecutive predecessors or maybe
another method.
 
J

Jan De Messemaeker

Hi,

In Excel there are two ways to drag down, and you do not specify which one
you want.
If you want to copy the same value down, there are two ways in Project: you
can "grab" the lower left corner and drag as in Eccel or wou can specify the
range and type Ctrl+D to copy down.

If you want to increment the predecessor ID by 1 each time, that cannot be
done by dragging in Project. However, you can select the tasks to be
sequentuiially linked and click the "Link Tasks" icon on the Standard
Toolbar to link them in sequence.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

Mike Glen

Hi,

I think Jan meant the bottom RIGHT corner of the cell for the fill button.


Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top