P
PM Bart
Trial version of 2007.
I have a project with a number of subproject tasks driven by
interdependancies within the subproject. These tasks, need to timeshare a
resource (a machine). I would like to show the times that the machine is
being used as a rollup comprised of the tasks from the subprojects. I can do
this by copying the tasks and linking them, but then edits to the subproject
tasks are not necessarily reflected in the machine rollup and vice versa.
Is there a way to "mirror" or display a copy of a task within a project so
that it shows up in multiple rollups? If the same task ID could be displayed
in multiple locations in the Gantt and would allow edits to the task to be
applied to all instances of the task that would be a great feature as well.
I have a project with a number of subproject tasks driven by
interdependancies within the subproject. These tasks, need to timeshare a
resource (a machine). I would like to show the times that the machine is
being used as a rollup comprised of the tasks from the subprojects. I can do
this by copying the tasks and linking them, but then edits to the subproject
tasks are not necessarily reflected in the machine rollup and vice versa.
Is there a way to "mirror" or display a copy of a task within a project so
that it shows up in multiple rollups? If the same task ID could be displayed
in multiple locations in the Gantt and would allow edits to the task to be
applied to all instances of the task that would be a great feature as well.