jlg
In my project plan, i have milestones with predecessors. Once those
predecessors are 100% complete, should Project be marking the specific
milestone they are tied with as 100% complete?
I noticed in this user group in late Oct 2005, that Jan you shared
macro code to mark milestones complete based upon previous tasks. I am
asking for a slight twist upon that - i.e., will Project update a '%
complete' field for a specific milestone whose predecessors are 100%
complete?
thanks for your help!
jlg
predecessors are 100% complete, should Project be marking the specific
milestone they are tied with as 100% complete?
I noticed in this user group in late Oct 2005, that Jan you shared
macro code to mark milestones complete based upon previous tasks. I am
asking for a slight twist upon that - i.e., will Project update a '%
complete' field for a specific milestone whose predecessors are 100%
complete?
thanks for your help!