A
Al Gardiner
I have a master project with dozens of projects in it. I've set priorities
for each and attempt to level these. I use 'hour by hour' or 'day by day'
and I choose 'Priority, Standard'. All seems to be fine from project to
project in that they generally use resources the way I intend. My problem is
that for most of the projects (specifically, the ones that have 0%
completion) the first task is always delayed until some unusual date far
beyond the other tasks for which it is a predecessor. For example, Project A
has Tasks 1 through 4 linked successively. Task 1 is scheduled for September
while tasks 2, 3, and 4 get scheduled in order during June. The tasks
individually have default priority of 500. Can anyone point me to some
things to look for in resolving this?
for each and attempt to level these. I use 'hour by hour' or 'day by day'
and I choose 'Priority, Standard'. All seems to be fine from project to
project in that they generally use resources the way I intend. My problem is
that for most of the projects (specifically, the ones that have 0%
completion) the first task is always delayed until some unusual date far
beyond the other tasks for which it is a predecessor. For example, Project A
has Tasks 1 through 4 linked successively. Task 1 is scheduled for September
while tasks 2, 3, and 4 get scheduled in order during June. The tasks
individually have default priority of 500. Can anyone point me to some
things to look for in resolving this?