It seems like when I level resources, that the following happens
1. That my summary tasks finish dates no longer match the finish date of the longest sub-task
2. That the Predecessors links I have in place before leveling are not changed with the finish date change that happens because of the leveling. (ie. Task1 is a Predecessor of task2. TASK2 start is after TASK1 Finish, After leveling, TASK1 finish is changed because of leveling, but my TASK2 start is not changed to show the impact
Can someone tell me if this is normal or how fix or work around this problem
Many thanks
Brad
1. That my summary tasks finish dates no longer match the finish date of the longest sub-task
2. That the Predecessors links I have in place before leveling are not changed with the finish date change that happens because of the leveling. (ie. Task1 is a Predecessor of task2. TASK2 start is after TASK1 Finish, After leveling, TASK1 finish is changed because of leveling, but my TASK2 start is not changed to show the impact
Can someone tell me if this is normal or how fix or work around this problem